SOP for Preventive Maintenance

To lay down the procedure for preventive maintenance. This SOP shall be applicable for all preventive maintenance of all types of equipment and systems.

RESPONSIBILITIES

Technician/ officer/executive

ACCOUNTABILITY

Head of Engineering

Procedure 

A preventive maintenance plan shall be prepared at the month end of December and June for the next six months.

Whenever the new types of equipment are installed, shall be incorporated into the preventive maintenance plan at the end of the month as a supplement to the original preventive maintenance plan.

A preventive maintenance schedule for every month shall be prepared based on the preventive maintenance plan.

Preventive maintenance shall be carried out as per the scheduled date.

A preventive maintenance schedule for next month shall be issued to concerned the department in the last week of the running month.

A preventive maintenance checklist shall be prepared based on our past experience, maintenance manuals, and manufacturer’s recommendations for every type of equipment.

Each checklist shall be approved by the head of engineering.

The checklist no shall be an alphanumeric system comprised of 12 characters the first preventive maintenance checklist prepared for the equipment belonging to the production department will be numbered.

Take necessary work permits for the concerned department wherever required.

Ensure the right quality of consumables including oil & grease are available.

Ensure the main switch of the machine is turned off, the fuse has been removed wherever available and utilities are isolated whenever required, Tag the UNDER MAINTENANCE label to the types of equipment.

Standard operating procedure for preventive maintenance

Preventive maintenance should be carried out as per the preventive maintenance checklist and tick-marks the checks.

In the case, of repeated breakdowns observed during operation, corrective action should be planned during preventive maintenance.

After completing the preventive maintenance take a machine trial and remove the UNDER MAINTENANCE label.

If the machine status is satisfactory, hand over the machine to the respective department representative. In the case of utility and HVAC equipment, performance is to be verified by a responsible engineer.

If the machine status is not acceptable take appropriate corrective action.

Symbolically update preventive maintenance schedule and plan as indicated below

O = Planned =   Executive

O    =    Planned but not done

Rescheduled & Done

In case any major part is to be replaced, which may affect the machine's performance should take place through a change control procedure.

In case a machine is not available for preventive maintenance due to the production plan, the preventive maintenance can be rescheduled within 7 days of the scheduled date.

ABBREVIATIONS

      SOP:               Standard Operating Procedure

      QA:               Quality Assurance

     QC:               Quality Control

No.         :               Number

REFERENCE:

                Nil

>Process Control System Audit | Types of Audits

>Integrated Management System Manual (IMSM)

BANTI SINGH

Hi I'm Banti Singh, a Chemical Engineer! Welcome all of you to my blog. If you got the information right? Share the information. All of you Thank you

Thanks to visit this site.

Post a Comment (0)
Previous Post Next Post